First Floor Block Walls completed 9 Mar 2018 Slab, Ground Floor Pillars and Block Walls completed 25 Jan 2018 Building Fill, Screw Piles and Footings Completed 21 Dec 2017

First Floor Block Walls completed 9 Mar 2018

Slab, Ground Floor Pillars and Block Walls completed 25 Jan 2018

Building Fill, Screw Piles and Footings Completed 21 Dec 2017